Getting your keys: vacant possession and the defect checklist

Short answer: Under the standard sale agreement for new strata homes (Schedule H), the developer hands over vacant possession only once there is a certificate of completion and compliance, the strata title has been issued, and water and electricity are ready for connection. You have 24 months from that date to report defects, and the developer must repair each defect within 30 days of your written notice. If it doesn't, you can repair it yourself and claim the cost from money held back by the developer's lawyer.

The clock starts even if you don't collect the keys. Thirty days after the developer's notice to take possession, you are treated as having taken it. Maintenance charges and the 24-month defect period both start then.

The key dates under Schedule H

WhatRule
Delivery of vacant possessionWithin 36 months of the sale agreement
Late deliveryThe developer pays liquidated damages at 10% a year of the purchase price, counted day by day
Conditions for handoverCertificate of completion and compliance, strata title issued, water and electricity ready for connection
Deemed possession30 days after the notice to take possession
Maintenance chargesFrom vacant possession; the first four months are paid in advance
Defect liability period24 months from vacant possession, for your unit and the common property
Developer's repairsWithin 30 days of your written notice, at the developer's cost

From the Housing Development (Control and Licensing) Regulations 1989, Schedule H, clauses 19, 25, 27 and 30. Your own SPA is the final word; check its dates.

On the day: the inspection checklist

Walls, floors and ceilings

  • Cracks, uneven paint, damp patches or stains
  • Hollow floor tiles (tap them), chipped tiles, uneven grout
  • Ceiling stains that could mean a leak from above

Doors, windows and glass

  • Doors and windows open, close and lock smoothly
  • Gaps around frames, scratched or cracked glass
  • Sliding doors to the balcony seal against rain

Wet areas

  • Run every tap and shower; check water pressure and drainage
  • Floor slopes towards the drain, with no standing water
  • No leaks under sinks and around the toilet

Electrical

  • Every switch, socket and light works (bring a phone charger to test sockets)
  • The distribution board is labelled
  • Air-conditioner points and the water heater point are where the plan shows

Paperwork

  • Keys, access cards and remote controls counted against the handover list
  • Meter readings noted and photographed
  • Every defect photographed, listed and submitted in writing, with a copy kept

If the developer doesn't fix a defect

  1. Report it in writing during the 24 months, with photos.
  2. Allow 30 days for the repair.
  3. If it isn't repaired, give notice, have it repaired yourself and claim the cost from the stakeholder sum held by the developer's lawyer, as the SPA allows.
  4. If you still can't settle it, you can file a claim against the developer at the Tribunal for Homebuyer Claims, for up to RM50,000, without a lawyer.

Living overseas?

You don't have to fly in for the handover. You can authorise someone in writing to collect the keys and inspect for you, or hire a defect inspection company. Make sure they submit the defect list in your name and send you a copy. Report defects as early as you can: the 24 months run whether you're in Malaysia or not.

Buying off-plan and living overseas? Ask me how handover works for the project you're looking at. Ask on WhatsApp →

Before you pay a booking fee

Foreign Investor's Due Diligence Checklist (free)

The checks to make before you commit to any property in Malaysia.

Get the free checklist

Prefer to talk it through? Ask Seann on WhatsApp

Frequently asked questions

How long is the defect liability period in Malaysia?

24 months from the date you take vacant possession, under the Schedule H sale agreement for new strata homes. It covers your unit and the common property.

How long does the developer have to fix a defect?

30 days from your written notice. If the defect isn't repaired, you can repair it and claim the cost from the stakeholder sum held by the developer's lawyer.

What does the developer pay if the handover is late?

Liquidated damages at 10% a year of the purchase price, counted day by day, if vacant possession is late beyond the date in the sale agreement (usually 36 months).

When do I start paying maintenance charges?

From vacant possession. Under Schedule H the first four months are paid in advance.

Do I get my strata title with the keys?

Under the current Schedule H, the strata title must be issued before vacant possession, so the title and the keys come together.

Keep reading

About the author

Seann Siow portrait

Seann Siow is a registered estate negotiator in Kuala Lumpur (REN 34312) with more than 10 years in property. He helps foreign buyers and relocating families buy new condominiums in Kuala Lumpur.

More about Seann

Sources

Updated 16 November 2026.

  • Housing Development (Control and Licensing) Regulations 1989, Schedule H (as amended), clauses 13, 19, 25, 27, 29 and 30 — copy at rehdamelaka.org.
  • Housing Development (Control and Licensing) Act 1966 (Act 118), Part VIA (Tribunal for Homebuyer Claims, awards up to RM50,000).
  • Inspection checklist: Seann Talk Property.

General information, checked on the date shown, not legal, tax, immigration or financial advice. Rules and fees change; confirm them for your own case with the relevant government agency, a lawyer or a licensed adviser. All prices, fees, taxes and figures on this page are based on information current at the date checked, are not guaranteed, and may change in future. Seann Siow, REN 34312.